1998The Gloucester High School reopened after its renovation.Arts and Culture, Government and Public Service, Location and Setting, Buildings & Architecture, Education

The $28 million project started in 1994. Three years later, the contractor, TLT Construction, was being criticized as “grossly deficient and unsatisfactory,” including complaints of missed deadlines, poor workmanship, and cost discrepencies. The school reopened in 1998.